The Winter Olympic Village will open on January 27 next year!
Recalling the time of the construction of the Winter Olympic Village project
The ZTM tower crane is proud to participate in the construction!
We work with the Beijing Urban Construction Iron Army
Furious and sonorous!
Today, from the perspective of major media
Thread of time
Relive the story of ZTM tower crane helping Beijing Winter Olympic Village
SET OFF! RESPONSIBE FOR THE MISSION AND TRUST
On September 27, 2018, the Beijing Winter Olympic Village project officially started construction. The Beijing Winter Olympic Village project adopted a prefabricated steel structure building structure that was rarely used in China at that time. Beijing Urban Construction Group has very strict requirements for the safety, stability and performance of hoisting equipment. The equipment selection team inspected multiple brands, conducted rigorous demonstrations and selected the best ones. The ZTM intelligent tower crane ZTT7530 firmly assumed the heavy lifting task and served In this world-renowned national-level facility.
The ZTM tower crane ZTT7530 has been successively put into the lifting construction site of Beijing Winter Olympic Village since the beginning of December 2018. Xinhua News Agency published photos of the construction site of the ZTM Towers in the Winter Olympic Village on May 9, 2019.
On the morning of October 31, the project ushered in an important node for the main steel structure roofing: as the ZTM ZTT7530 tower crane hoisted the last steel beam of the 12# building, it was hoisted to the predetermined position on the roof smoothly and accurately. In the mode, the steel structure slowly descends, and the component installation and welding are successfully completed!
This marks the completion of the main steel structure of the 11 buildings in the first bid section of the Beijing Winter Olympic Village Talent Public Rental Housing Project 30 days in advance, laying a solid foundation for the full completion of the main structure before the end of the year.
From July 16 to the completion of the underground structure capping task, to October 31, the completion of the main steel structure capping. It took only 3 and a half months! The ZTM ZTT7530 tower crane witnessed the emergence of 11 buildings with the highest 17 floors and a height of 60 meters! Become a powerful stabilizer and booster for project progress
On June 26, 2020, the Beijing Winter Olympic Village residential area was fully completed and delivered to the Beijing Winter Olympic Organizing Committee for use, marking that the Winter Olympic Village has fully entered the Olympic time!
Beijing Winter Olympic Village is located on the south side of the Olympic Sports Center, with a total construction area of about 330,000 square meters and consists of 20 houses. Viewed from the air, this is a traditional three-entry courtyard. This design not only highlights the athlete-centered concept, but also reflects the characteristics of traditional Chinese culture. The competition will provide services to athletes and team officials from various countries. Among them, 2,260 beds will be provided during the Winter Olympics and about 500 during the Paralympics.